10 Special Conditions That Shift Risk on NZ Construction Projects
provan.ai
March 2026
Most NZS 3910 contracts are amended by Special Conditions before signing. Some amendments are routine housekeeping. Others fundamentally change the risk profile of the contract — shifting exposure, tightening deadlines, or removing protections that the standard form was designed to provide. This checklist covers the 10 most common and highest-impact Special Conditions, what they mean for each party, and the case law that shows what happens when they're missed.
NZS 3910 Clause 13.3.1 requires the contractor to give notice of a potential claim "as soon as practicable." Special Conditions frequently tighten this to a strict 10-working-day window from when the event occurred or should reasonably have been known — and make it an absolute bar. Miss it, and the claim is extinguished regardless of its merit.
NZS 3910 Clause 10.3 normally caps liquidated damages at 10% of the contract price. Deleting this cap means LDs run at the daily rate indefinitely for the duration of delay. On a $50M project with $15,000/day LDs, a 6-month delay generates $2.7M in damages — uncapped. The penalty doctrine (127 Hobson Street v Honey Bees [2020] NZSC 53) provides a legal backstop — but the threshold is deliberately high: a clause must be "out of all proportion" to the innocent party's legitimate interests or "exorbitant" before a court will intervene. This replaced the older "genuine pre-estimate of loss" test from Dunlop with a more permissive standard. In practice, a reasonable daily LD rate accumulating over an extended delay period will be nearly impossible to challenge, even if the total becomes substantial — meaning the practical risk of uncapped LDs remains significant.
NZS 3910:2023 note: The 2023 revision introduces an opt-in overall liability cap mechanism (clause 7.2) that may interact with LD provisions. Where the 2023 form is used, check whether this separate cap has been adopted and how it applies to LD exposure.
The Construction Contracts Act 2002 provides a default 20-working-day window to respond to a payment claim with a payment schedule. Special Conditions often shorten this to 15 or even 10 working days. Missing the window makes the full claimed amount a debt payable immediately — no discretion, no appeal.
Standard NZS 3910 allows variations to be valued by agreement, scheduled rates, or reasonable rates. This Special Condition restricts valuation to scheduled rates only and makes the Engineer's assessment final — removing the contractor's right to negotiate or dispute the valuation through the contract.
Clause 13.5 requires timely notice of delay events. Special Conditions often impose strict time limits (10 or 15 working days) and make compliance an absolute precondition to any EOT entitlement. Late notice = no extension, regardless of the legitimacy of the delay.
Removes any ceiling on the value of work the Engineer can instruct via variation. Combined with "Engineer's assessment final" clauses, this gives the Engineer significant unilateral power to direct additional work without a predetermined cost limit.
Standard retention under NZS 3910 Clause 12.4 is typically 10% (capped at 5% of contract value). Special Conditions may increase the percentage or attempt to modify the retention trust obligations imposed by the CCA. The CCA requires retention money to be held on trust — this cannot be contracted out of.
NZS 3910 Clause 11.3 defines Practical Completion and the Engineer's certification obligation. Special Conditions often expand the criteria — requiring completion of commissioning, third-party certifications, operational readiness, or CCC before PC can be certified. This delays the PC date and extends the contractor's liability period.
Under NZS 3910, the Engineer has a dual role — acting as the owner's agent for some functions and as an independent certifier for others (valuation, PC, EOT). Special Conditions sometimes blur or remove this independence requirement, making the Engineer purely the owner's agent in all functions.
Some Special Conditions attempt to modify or exclude provisions of the Construction Contracts Act 2002 — for example, restricting the right to suspend work for non-payment, modifying adjudication rights, or altering payment claim procedures. Under s12 of the CCA, provisions that attempt to contract out of the Act are void and unenforceable.
Use this on your next NZS 3910 contract review. Tick each item as confirmed.